Monday, March 14, 2011

Update 14 March

Kia ora koutou.

Today we had builders on site! Hooray!

Things happening today:


  • We finished emptying the resource room and have put the reading resources onto the library shelving that has been moved to the back of the hall.
  • Isabel's office was emptied.
  • Room 6 has been moved to the staffroom. All classes have now been moved to where they needed to be moved.
  • Resources not needed in the short term have been put into a container.
  • Konica Minolta came and moved the photocopier from the resource room to the APs' office.
  • We have salvaged a few items from Rooms 5-8.
  • The builders have been working to ease the doors and seal off the library and resource area.
  • A camera has been put down through our sewerage pipes to see if they are intact.
  • We have located a break in our water main.
Things we are working on:
  • We still have no power coming in to the school off Sandy Ave and are working on getting an answer (not from the answer machine) from Orion.
  • Getting a drain layer to come and repair our water main.
  • Getting an answer about our sewerage situation.
  • Getting a date when our Room 5-8 block will be demolished. We want this to have happened before the children return to school but the Public Holiday on Friday doesn't help us.
  • We need to access two more containers - one for maths resources and one to use a PE shed. These have been ordered.
  • Getting an answer on what will happen with the Library to Room 4. Repair or rebuild?
OSCAR After School Programme Continues

The Oscar After School Programme will continue as usual when school commences. It will be based in our new Learning Studio not in the hall.

We have a Project Team Meeting tomorrow so I will update again after that and as new information becomes available.


1 comment:

  1. Let me know when it's demolishing time and I'll bring my hard hat, sledge hammer and Flip. Elizabeth